What is correct about building permits regarding a main floor addition?

  1. A building inspector ultimately has the authority to issue a 'stop work' order if the addition does not meet standards.

  2. A building inspector can only inspect with approval from the property owners.

  3. The addition must comply with the Ontario Municipal Standards Code.

  4. The final step in the process is the review of plans by the municipal building department.

The correct answer is: A building inspector ultimately has the authority to issue a 'stop work' order if the addition does not meet standards.

A building inspector ultimately has the authority to issue a 'stop work' order if the addition does not meet standards because building permits are essential to ensure that construction projects comply with safety and zoning regulations. If the addition does not meet the required standards or violates any building codes, the building inspector has the authority to issue a 'stop work' order to halt construction until the issues are rectified. This is crucial to maintain the integrity and safety of the property and surrounding areas. In contrast: - Option B stating that a building inspector can only inspect with approval from the property owners is incorrect because building inspectors are authorized to carry out inspections without needing approval from property owners. Inspections are necessary to verify compliance with regulations and standards. - Option C is incorrect as it mentions the addition must comply with the Ontario Municipal Standards Code. While it is important for the addition to comply with building codes and regulations, the Ontario Building Code is the primary regulation governing building construction in Ontario, not the Ontario Municipal Standards Code. - Option D is incorrect because the final step in the process involves the issuance of the permit after review and approval of the plans by the municipal building department, not just the review itself.